Order Quantity:100K pcs,      Fabric: S/J,      GSM:160gsm,          Gadge:24gadge


Checklist: 

  1. Ensure the inventory report is updated and collected from the store.
  2. Verify and approve requisition requests to the store.
  3. Confirm SOP compliance for fabric relaxation is maintained.
  4. Collect and review the fabric inspection report before cutting.
  5. Verify lab test reports as per buyer requirements.
  6. Prepare and monitor the cut order plan (schedule).
  7. Finalize line style selection (production plan).
  8. Conduct test cutting before bulk production.
  9. Collect and verify fabric consumption reports.
  10. Perform measurement checks against approved samples.
  11. Adjust if deviations are found.
  12. Obtain bulk cutting permission from QA/merchandiser.
  13. Conduct daily quality checks and inform the merchandiser if any deviation is found.
  14. Check and monitor CAD marker efficiency.
  15. Ensure printing parts are sent and received properly.
  16. Ensure embroidery parts are sent and received properly.
  17. Monitor and record cutting wastage.
  18. After production, check the rejection percentage and take corrective action.