Allowance for SMV calculation
- Allowance is basically some additional time for needs ( drink water, Cleaning fatigue and delays).
- Allowance can be given as a percent of work time .
- Allowance are the interruptions that occur during the working day.
- Personal allowance-5%
- Fatigue allowance-5%
- Delay/Machine allowance-5%
- Contingency allowance-5%
- Personal Allowance: drink water, going to wash room and Clean up after operations.
- Fatigue Allowance: Standing with a load, walking with a load, lifting a load, anxiety, monotony, temperature, sound, illumination
(একটি বোঝা নিয়ে দাঁড়িয়ে থাকা, একটি বোঝা নিয়ে হাঁটা, একটি বোঝা উত্তোলন,
উদ্বেগ, একঘেয়েমি, তাপমাত্রা, শব্দ, আলোকসজ্জা) - Delay Allowance: Machinery is kept in repair, tool breakage, minor adjustment.
- Contingency Allowance:Power Failure,Input gap